The first step in the creation of a PERT/CPM chart is to ____.

The first step in the creation of a PERT/CPM chart is to ____.



a. determine the logical order of project tasks
b. identify the graphical planning aids to use
c. identify all the project tasks
d. determine the status of all tasks



Answer: C